We will be completing the installation and testing of essential safety equipment at Marcheys House Level Crossing (see image below for location) in advance of the re-opening of the Northumberland Line on the following dates and times.
· From 10pm on Saturday 20 July to 10pm on Monday 22 July (24/7).
· From 10pm on 6am each night from Monday 22 July, finishing at 6am on Thursday 1 August.
The works will require a full road closure for vehicles at the level crossing. A diversionary route, which has been agreed with the council, will be clearly sign posted.
There will be no pedestrian access across Marcheys House Level Crossing between 10pm on Saturday 20 July to 10pm on Monday 22 July. A shuttle bus will be provided to support pedestrian users during this closure. Pedestrian access will be maintained during the overnight works Monday 22 July, finishing at 6am on Thursday 1 August.
Shuttle Bus Information
We understand that working near your homes and working overnight is far from ideal and we are sorry in advance for any disruption these essential works may cause. Our teams have been briefed and will be mindful when carrying out this work, making sure all the relevant mitigations are in place to avoid excess noise.