Apr 16Great Work in MarchAs well as the work to build stations, car parks and bridges ahead of the passenger services returning this summer, there's also a lot of...
Apr 11Signals are good for return of passenger trainsThe return of passenger rail services on the Northumberland Line has moved another step closer following the completion of major...
Apr 8New Equipment at Bedlington North Foot CrossingBedlington North foot crossing, between Barrington Road and Blenheim Drive estate, has seen some significant changes as part of the...
Mar 28March NewsletterOur March newsletter is out now and there's a lot of work going on as we get ready for passenger services to start this Summer. Click on...
1 day agoProgress on track at BedlingtonNow that the track work and resignalling works are complete at Bedlington, we look back at some of the works taking place to help to...
1 day agoHartley Level Crossing Upgrade WorksWe will be installing and testing the new level crossing equipment at Hartley Level Crossing from 10pm on Sunday 5 May to 10pm on Friday...
5 days agoInstallation of Conductor Facility at AshingtonWe'll be carrying out works to install the new conductor facility for Northern Trains staff on Sunday 21st April. The works will see the...