top of page

Overnight Level Crossing Closures at Blyth Bebside (2nd, 3rd & 4th November)

We will be undertaking works to complete the upgrade of the level crossing on Front Street, in the area shown below, ahead of the reopening of the line to passenger trains later this year.



The works will be undertaken on the following dates and times:

·        From 10:30pm on Saturday 2 November to 6am on Sunday 3 November.

·        From 10:30pm on Sunday 3 November to 6am on Monday 4 November.

·        From 10:30pm on Monday 4 November to 6am on Tuesday 5 November.

 

There will be a full road closure over the crossing while works are taking place. There may be some localised disruption due to noise, however we will limit this where possible, including by turning equipment off when not in use.  A diversion will be clearly sign posted and a free shuttle bus will be provided to support pedestrians during the closure.


Shuttle Bus Timetable


We understand that working near your property and working overnight is far from ideal and we are sorry in advance for any disruption these essential works may cause. Our teams have been briefed and will be mindful when carrying out this work, making sure all the relevant mitigations are in place to avoid excess noise.


For any queries about this track work and associated road closures please call the Network Rail National Helpline on 03457 11 41 41, which is available 24/7 