With the mining works treatment now nearing completion, we are moving into the next phase of construction which will include the installation of the platform.
The next phase of work includes activities which must be done when trains are not running on the line.
We will be carrying out work on the following dates and times:
· From 10.30pm on Friday 11 October to 5.30am on Monday 14 October
· From 10.30pm on Saturday 19 October to 5.30am on Monday 21 October
· From 10.30pm on Saturday 26 October to 5.30am on Monday 28 October
· From 10.30pm on Saturday 2 November to 5.30am on Monday 4 November
· From 10.30pm on Friday 8 November to 5.30am on Monday 11 November
· From 10.30pm on Friday 15 November to 5.30am on Monday 18 November
· From 10.30pm on Friday 22 November to 5.30am on Monday 25 November
· From 10.30pm on Saturday 30 November to 5.30am on Monday 2 December
· From 10.30pm on Saturday 7 December to 5.30am on Monday 9 December
If you wish to be updated directly about the type of works on each weekend, please contact rail@northumberland.gov.uk or call the Northumberland County Council contact centre on 0345 600 6400 and provide us with an email address.
What to expect during the works
During this work there is potential for noise, site lighting and vibration, but we will aim to keep disruption as minimal as practically possible and within the terms agreed with North Tyneside Council. We have continuous noise monitoring equipment installed onsite to capture in real-time the noise levels being generated.
We understand that working near your homes and working at weekends and overnight is far from ideal, and we apologise in advance for any disruption these works may cause. The continuous access to the track for longer periods of time enables us to complete this essential phase of works as quickly as possible.