Seaton Delaval Construction Update

Work to progresses the new Seaton Delaval station is ongoing. Up and coming works to complete the station which will take place over the next couple of months include:

·        Extending site into the neighbouring field behind Whytrigg Close and Wheatridge for drainage and footway works.

·        Diverting the current temporary Public Right of Way.

·        Compacting stone to form new access/ footways across the field.

·        Installation of drainage around the new access/ footways.

·        Continuing works to the car park.

·        Completion of access and surfacing the road for the A192.

·        Installation of new traffic signals by Newcastle City Council.


What to expect during this period

During this period, there is potential for some impact for people living close by, however every effort will be taken to limit it where possible including noise and vibrations. Heavy compacting equipment will need to be used to complete the footways and car park up until the works are complete however, we will aim to keep noise and vibration to a minimum where practically possible. Noise monitors are in place which continuously report data. This is monitored by the contractor’s Safety, Health and Environmental team.

 

Notice of relocation of diverted Public Right of Way (PRoW)

In order to install drainage and put in the new permanent path for residents accessing the new station from east, the currently diverted PRoW will need to be diverted to the east of its current location. This diversion will be in place until the opening of the new footway. Works to extend the site boundary to enable this work to take place will start on Wednesday 24 July 2024 and is expected to be completed in September 2024. Works will take place during the day, through the week and on weekends, between the hours of 8:00 am – 6:00 pm. Please note that access to the diverted PRoW will be open to the public throughout this time. Please see image below for exact location.  

Advance notice of traffic management on A192, Astley Road

In order to complete the asphalting, surfacing and lining of the new access road (bellmouth) to the station, there will be lane closures controlled by temporary traffic lights on the A192, between The Hastings Arms and the roundabout outside of Delaval Court. These will be in place from 9:30am to 3:30pm and (if required) 7:30pm and 11:50pm from Monday 12 August 2024 until Wednesday 28 August 2024.


In addition to the daytime lane closures, there will also be a full road closure overnight from 11:50pm until 5:30am, on the above dates. Advanced notice signage will be in place ahead of the full road closures and diversion routes will be clearly signposted throughout. There will be access for pedestrians at all times and special arrangements are in place for the bus services along Astley Road to remain on their usual route.  Please note that additional traffic management may be in place during this period carried out by third parties.  