top of page

Level Crossing Upgrade Works at Green Lane in Ashington

We will be completing the installation and testing of essential safety equipment at Green Lane Level Crossing in advance of the re-opening of the Northumberland Line on the following dates and times.


·        From 10pm on Saturday 6 July to 10pm on Tuesday 9 July (24/7).

·        From 10pm to 6am from Tuesday 9 July to 6am on Monday 22 July (overnight only).

The works will require a full road closure at the level crossing. A diversionary route, which has been agreed with the council, will be clearly sign posted.


There will no pedestrian access across Green Lane Level Crossing from 10pm Saturday 6 July to 10pm on Tuesday 9 July. Pedestrian access will be maintained however during the overnight works between Tuesday 9 July to Monday 22 July.


We understand that working near your homes and working overnight is far from ideal and we are sorry in advance for any disruption these essential works may cause. Our teams have been briefed and will be mindful when carrying out this work, making sure all the relevant mitigations are in place to avoid excess noise.


For any queries about this track work and associated road closures please call the Network Rail National Helpline on 03457 11 41 41, which is available 24/7.


Comments


bottom of page